The Langfang Thermal Power Phase II Unit 4 of Guodian Power passed the 168-hour test run.

date
13/08/2026
According to news from the State Power Investment Corporation's official WeChat account, at 23:55 on August 12, the Unit 4 of the 2350MW capacity replacement project of the Langfang Thermal Power Phase II of the State Power Investment Corporation passed a high-standard 168-hour full-load trial operation, with all performance indicators meeting design requirements, and officially entered commercial operation. With this, the Langfang Thermal Power Phase II project has achieved full capacity commissioning.