Xinhan Xincai: The third workshop of the raised investment project has entered the trial production stage.

date
15/06/2026
New Han New Materials Announcement: The company has completed the construction of the main body, equipment installation, project commissioning, system pressure testing, and various acceptance work such as environmental protection and fire safety for the second phase of the "Annual Production of 8,000 Tons of Aromatic Ketones and its Supporting Projects" in three workshops and associated facilities. The company's project trial production plan has been approved by experts and relevant departments, and the company has also obtained a new "Pollution Discharge Permit" issued by the environmental protection department on June 12, 2026, in accordance with requirements. The three workshops are now ready for trial production, marking the entry of the three workshops and associated facilities of the "Annual Production of 8,000 Tons of Aromatic Ketones and its Supporting Projects" into the trial production phase.