Jinshi Technology: plans to invest in a 200MW/400MWh electrochemical standalone energy storage station project in Guangdong Province.

date
02/03/2026
Jinshi Technology Announcement: The company held the twenty-third meeting of the third board of directors on February 28, 2026, and approved the "Proposal on the Intended Investment in the Construction of an Independent Energy Storage Power Station Project." The company plans to invest in a 200MW/400MWh electrochemical independent energy storage power station project in Guangdong Province through its subsidiary using its own funds or self-raised funds, with an estimated total investment of approximately 500 million yuan and a construction period of about 6 months. The project aims to accelerate the company's strategic layout, enhance core competitiveness, and sustainable development capabilities.