China SkyOne: Jilin Liaoyuan Hydrogen Energy Phase I Project is scheduled to complete construction by the end of June and to test the products by the end of the third quarter.
On March 1st, China Tianying announced at an investor relations event that the first phase of Jilin Liaoyuan Hydrogen-based Energy Integration Benchmark Project is planned to be completed by the end of June 2026. The project will go through testing and debugging in July and August, with product testing expected to be completed by the end of the third quarter. Currently, the central control room has been basically completed, all electrical equipment in the plant has been installed, and 98 wind turbines are planned to be installed by the end of June. Carbon dioxide and hydrogen compressors are already in place, and around 50,000 tons of straw have already been collected and stored.