Huainan Mining: Jugneng Power Generation Unit 2 passes 168-hour trial operation.

date
01/07/2026
Huibei Mining announced that the second unit of the 2660MW ultra-supercritical coal-fired power generation project, which is under construction by its subsidiary Juhong Electric Power, has successfully completed a 168-hour full-load trial operation and entered into commercial operation mode. Located in Lieshan District, Huaibei, Anhui Province, the project is an important support project for Anhui Province's "14th Five-Year Plan" for energy and power, with a designed annual power generation capacity of 5.94 billion kilowatt-hours. Currently, preparations for the 168-hour trial operation of the first unit are steadily progressing, and after all units are put into operation, it will help alleviate the tight supply and demand of electricity in Anhui and expand the company's coal-electric integration scale.