Binhai Energy: The first phase of the 150MW wind power project, which integrates wind power generation, energy storage, and power grid connection, is expected to be put into operation soon.

date
30/06/2026
Binhai Energy stated on the interactive platform on June 30 that the basic construction of the company's Youwanghe Storage Green Power Phase 1 150MW wind power project has been completed, and physical connections have been established with no risk of construction failure. The project is currently undergoing the final procedures for grid connection and dispatch, and is expected to start operation soon. The specific date of operation will depend on the progress of the procedures.